Skip to content

Infrastructure · 23 November 2026 · 5 min read

ERCOT Sets Dec. 4 Opt-In Deadline to Publish Locations, Power, and Water Use for 177 GW Texas Data Center Queue

With 33 Texas projects requesting over 1 GW each and 41% of capacity concentrated in arid West Texas, ERCOT will report on Dec. 10 how many developers agreed to disclose their power and water footprints.

Transmission towers, a substation, and a power station with cooling towers, with wind turbines beyond.
A photograph of transmission lines, a substation and a power station, with wind turbines in the distance. It is not one of the 433 surveyed projects, and it is not a data centre.

The Electric Reliability Council of Texas (ERCOT) has set a December 4, 2026 deadline for data center developers to opt in to public disclosure ahead of a December 10 report to the Public Utility Commission of Texas (PUC) detailing project locations, electricity demand, and water consumption (The Texas Dispatch, Nov. 23, 2026).

The transparency push follows Governor Greg Abbott’s August 3, 2026 directive to ERCOT and the PUC and arrives as state policymakers confront an unprecedented surge in hyperscale interconnection requests—one that threatens to reshape transmission planning and groundwater politics across West Texas.

Technical & Financial Breakdown

According to ERCOT’s November 5 survey summary submitted to the PUC, 433 data center projects responded—including all 245 facilities seeking 75 megawatts (MW) or more—collectively requesting approximately 177 gigawatts (GW) of grid capacity (The Texas Dispatch, Nov. 23, 2026).

Key figures from the filing highlight the extreme scale and geographic concentration of the queue:

  • Gigawatt-Scale Campuses: Thirty-three individual projects requested more than 1 GW of power each.
  • West Texas Concentration: Roughly 41% of requested capacity—approximately 73 GW—is concentrated in West Texas, where wind, solar, and natural gas supplies are abundant but groundwater and high-voltage transmission corridors are constrained.
  • Financial Gatekeeping: Separately, large Texas data centers requesting 75 MW or more now owe $100,000 upfront plus $50,000 per MW in financial security deposits (equivalent to $50 million in security for a 1 GW campus), raising capital barriers for speculative land-option developers.

Under ERCOT’s disclosure rules, the grid operator will publish project-level locations, power demand, and water usage on December 10 only for projects whose developers consent by December 4, while reporting to the PUC the overall share of developers that agreed to transparency.

Second-Order Implications

Even if a substantial fraction of the 177 GW queue represents duplicate or speculative site shopping across competing counties, the sheer volume forces Texas regulators to scrutinize both grid stability and municipal water availability. Developers that decline to opt in by December 4 risk intensifying local legislative pushback—particularly as Texas lawmakers already advance groundwater-verification bills (such as House Bill 1262) and permitting setbacks across the state.

Caveats & Open Questions

Requested megawatts in ERCOT’s survey do not represent finalized interconnection agreements or funded construction schedules, and many developers submit overlapping capacity requests while competing for land and power purchase agreements. ERCOT has not yet disclosed how many of the 433 respondents have consented to public release or how much of the 177 GW queue has posted the new $50,000/MW security deposits .